PERMIT 2016-010817 PP
5205 S SCOUT ISLAND CIR
Final
Plumbing PermitAuxiliary WaterResidential
Scope of work
Install RPZ (Reduced Pressure Zone backflow preventer) at meter. To allow for thermal expansion install expansion tank or other approved device (pressure relief valve set @ 100lbs (house side)) test RPZ and perform CCT (Cross Connection Test) label per PDR (Purple pipe purple box lids hose bibs labeled non-potable if tied to auxiliary water source) check all boxes that apply. If city backup is to be used for irrigation another RPZ must be installed and tested.
Record
Permit number2016-010817 PP
StatusFinal
Applied02-02-16
Issued02-16-16
Expires04-08-16
Completed04-08-16
Valuation—
Council district10
Official recordCity of Austin →
⚡ Alerts for work like this
Every new Plumbing Permit permit in 78731, in your inbox the morning it’s issued.
Set alert · Pro