PERMIT 2022-146429 EP
2311 WATERWAY BND
Final
Electrical PermitUpgradeResidential
Scope of work
Install a new 200A meter socket and ensure the meter height is within 4â-6â per utility company requirements. Replace the existing mast and riser if necessary. Install a new 125A main and distribution panel adjacent to the upgraded meter. Verify the grounding electrode system. Install a surge protection device in the new load center to comply with 2020 NEC requirements. Replace all the existing breakers. Interconnect with a 25A/2P PV breaker in the furthest position away from the main breaker in the upgraded main and distribution panel.
Record
Permit number2022-146429 EP
StatusFinal
Applied09-26-22
Issued09-27-22
Expires03-08-23
Completed03-08-23
Valuation—
Housing units1
Council district—
Official recordCity of Austin →
⚡ Alerts for work like this
Every new Electrical Permit permit in 78728, in your inbox the morning it’s issued.
Set alert · Pro