2401 CROWNSPOINT DR
Scope of work
1 access hole behind laundry wall excavating from garage door side of home 1 access on the exterior wall of guest bathroom 1 access at main line coming from master bath Total tunnel length 105ft Total excavation time : 4-6 days Total plumb time : 3-5 days Tunnel under master bath to replace existing drains Tunnel from laundry to kitchen sink drain from kitchen sink drain to guest bathroom We will reroute the kitchen and laundry drain to the guest bath directly to minimize tunnel length Replace toilet drain and tub drain including waste and overflow Guest lavatory drain is above ground tied into toilet vent line We will replace all excavated cast iron with schedule 40 pvc