800-905 W NORTH LOOP BLVD
FinalDriveway / SidewalksNewCommercial
Scope of work
***PER COORDINATION WITH 26-102167 RW THIS PROJECT HAS CLEARED THE ROW. CONFLICT CHECK REQUIRED FOR EXTENSION*** Construct new driveway approach of 38.33 FT and and curb & gutter of 11.4 FT. ***PER COORDINATION WITH 2025 054095 EX THEY WILL BE ACTIVELY WORKING DURING- START 5/19/25 & FINISH DATE: 11/07/25 DO NOT WORK WITHOUT ADDITIONAL COORDINATION*** Inspection paid through 2020 016804 000 00 SSI
Record
Permit number2025-111531 DS
StatusFinal
Applied09-03-25
Issued10-22-25
Expires10-22-26
Completed10-22-26
Valuation-
Council district-
Official recordCity of Austin →
Contractor
No contractor on file (often owner-permitted work).
⚡ Alerts for work like this
Every new Driveway / Sidewalks permit, in your inbox the morning it’s issued.
Set alert · Pro