11200 LAKELINE MALL DR UNIT VC09
FinalScope of work
We will add 60ft of 1-1/4 black iron gas pipe that will be feeding 3 separate grill/burners located next to each other in this unit these three grills/burners are the only fixtures using gas. We will attached our new gas line to the existing gas valve in the ceiling. We will run 3/4 branch lines from the 1-1/4 gas main for each individual burner grill. We will properly supported the gas lines and have placed stickers to identify piping use. We will install an additional gas shut off on the vertical riser coming from the ceiling to the work floor area each 3/4 branch will have a gas shut off for servicing purpose in the future. currently this unit has a gas meter pulled off due to change of tenant we will gas pressure test the whole line completely to ensure no leaks are present after the new gas line is added we will have the whole gas system on test for unit vc09.
Record
Every new Plumbing Permit permit in 78613, in your inbox the morning it’s issued.
Set alert · Pro